The BIM execution plan

The BIM execution plan is the team’s agreement on how information will be produced and shared. Learn what goes in it and how to keep it useful rather than a document nobody reads.

In this lesson you will

  • List the key sections of a BEP
  • Understand pre- and post-appointment BEPs
  • Define model breakdown and responsibilities
  • Keep the BEP practical and current

Pre- and post-appointment

In ISO 19650, a pre-appointment BEP is submitted with a tender to show how the team will meet the EIR. The post-appointment BEP is the detailed, agreed plan for delivery. Both answer: who produces what information, how, when, and to what standard?

What goes in

  • Project information, goals and BIM uses.
  • Roles and responsibilities, including an information manager and model owners.
  • Standards: naming, classification (e.g. Uniclass), drawing and modelling standards.
  • Software and versions for each party; exchange formats (native, IFC version, PDF).
  • Coordinates: origin, survey point, true north, units, levels naming.
  • Model breakdown: which models exist (by discipline, zone, level) and who owns them.
  • Level of Information Need per stage.
  • Exchange schedule, coordination meeting cadence and clash tolerances.
  • CDE workflow, approvals and security.
  • Quality assurance: checks before sharing.

Model breakdown

Decide early how the building is split into models — architecture per building or per level, structure, each services discipline, site — and who owns each. Good breakdown keeps files workable and responsibilities clear.

Keep it alive

A BEP that's written once and filed fails. Keep it short, make the coordinate and naming sections easy to find, review it at each stage, and version it in the CDE. Onboard every new team member with it.

Exercise

Draft a one-page BEP summary

  1. For a small two-storey office, list the models, owners and software.
  2. Define coordinates, units and level names.
  3. Set an exchange cadence and clash tolerances.
  4. List three QA checks before sharing a model.

You should end up with: A practical one-page summary a team could use tomorrow.

Checklist

0 of 4 checked · saved on this device

Lesson quiz

1 / 4

A BEP should state the coordinate system and origin.

Finished this lesson?

Taking the quiz marks it complete too. Your course page picks up where you stopped.

Free KitWren tools that help

Free, independent learning material written for KitWren. We never provide software downloads, licence keys or cracks — use the official sources.