BIM coordination concepts

Coordination is where BIM pays off: finding clashes between architecture, structure and services before they reach site. Learn how the process runs and your role in it.

In this lesson you will

  • Explain federated models and why they're used
  • Run an interference check in Revit
  • Understand clash detection and issue tracking
  • Know the coordination cycle and responsibilities

Federated models

Each discipline owns its model: architecture, structure, mechanical, electrical, hydraulics. They're combined — federated — for coordination, often in Navisworks or a cloud coordination platform, rather than merged into one file. Each author remains responsible for their own model.

Interference checks in Revit

Collaborate › Interference Check finds elements occupying the same space between categories in your model or against a linked model — e.g. ducts vs structural framing. The report lists element IDs; use Show to find each one. It's useful for quick checks; large projects use dedicated clash tools.

A duct from the mechanical model passing through a steel beam from the structural model, with the intersection highlighted as a hard clash.Steel beam (structural model)Duct (mechanical model)Hard clashtwo objects occupy the same space
Figure: A clash between two models. Original KitWren diagram.

Clash detection and issues

Coordination tools run clash tests between model sets with rules and tolerances: hard clashes (overlap), clearance clashes (too close for insulation or maintenance) and duplicates. Clashes are grouped, reviewed, assigned and tracked.

Issues are often exchanged as BCF (BIM Collaboration Format) topics — a viewpoint, a screenshot, a comment and an assignee — that open directly at the problem in each author's software.

The coordination cycle

Typically weekly or fortnightly: each team uploads models by an agreed deadline; the coordinator federates and runs clash tests; a meeting reviews priorities; issues are assigned; authors fix their models; repeat. Agreed tolerances, clash priorities and naming live in the BIM execution plan. See the Navisworks course for the detailed workflow.

Quick reference

Command / toolHow to start itWhat it does
Interference CheckCollaborate tabFinds overlapping elements
Select by IDManage › InquiryFinds elements by ID
Coordination ReviewCollaborate tabReviews monitored changes

Common mistakes

  • Thousands of meaningless clashes.

    Test specific category pairs with tolerances; exclude insulation-to-lining touches.

  • Fixing another discipline's model yourself.

    Each author fixes their own model; raise issues instead.

Exercise

Find and report a clash

  1. Place a floor beam in a copy of your model that passes through a door head.
  2. Run an Interference Check between Structural Framing and Doors.
  3. Create a 3D view zoomed to the clash with a section box.
  4. Write a short issue: location, elements, proposed fix, who should act.

You should end up with: A clash found and reported clearly.

Checklist

0 of 4 checked · saved on this device

Lesson quiz

1 / 4

A clearance clash means…

Finished this lesson?